Dodge County CTH A Resurfacing Project

June 5, 2013

Due to continued adverse weather conditions, progress has been slower than expected. Barring any further delays, we will finish paving the southbound side of the roadway on June 6th.

We will then start paving the northbound lanes from the north end going south on June 10th. Weather permitting, we will be finished paving the northbound lanes by June 14th.

Please contact Zignego's project supervisor, John Zignego, with any questions.

Office number: 262-547-4700
Cell phone: 414-750-4812
E-mail: john@zignego.com

May 31, 2013

Due to the excessive wet weather we were unable to finish the southbound lanes this week. We should complete them by the end of the day on Tuesday, June 4th. In order to keep things moving, we are going to start on the north end at AW and work south to take advantage of the cured concrete. We will move the equipment on Wednesday, June 5th and set up to start paving the second side Thursday, June 6th. These changes are necessary to keep the project on schedule. This means the road will have to stay one-way southbound for the second side of paving. Zignego will let the residents know as we work out access for each one.

If we can start paving the second side on 6/6, we should complete the machine work by 6/12. After that we will work on the curb and gutter and hand pours at the intersections to finish the concrete work by 6/21, weather permitting.

May 22, 2013

Due to the rainy weather, paving has been delayed by a day. Zignego will now begin paving on 5/22/13. Traffic remains one-way (southbound) for the whole project at this time.

May 15, 2013

Zignego's crews have started setting stringline and trimming the roadway in preparation for pavement. Please remember that as stringline is set traffic will be one-way only (Southbound) during this phase of construction. We expect to have this phase completed by June 5, 2013.

May 6, 2013

This is a brief schedule and description of our proposal to deal with local traffic and access to your property during the resurfacing of CTH A from STH 33 north to CTH AW.

Please contact Zignego's project supervisor, John Zignego, with any questions.